Welcome to our blog!

This space is intended to provide a detailed weekly account of the ongoing activities within the scope of our project, offering a comprehensive insight into it.

public/team-building-team-collaboration-for-business-idea-teamwork-to-solve-problem-participate-to-work-together-for-success-concept-businessmen-and-businesswomen-team-up-to-solve-lightbulb-jigsaw-vector-1500w.jpg

Progress Update - 2nd Jun. - 7th Jun.

This week, in Part A, we integrated the load management algorithm with the mock-up model from Part C. Additionally, we conducted further testing and debugging of the algorithm, identifying and fixing several issues. In Part C, we completed the electrical wiring for the physical mock-up model and conducted a series of experiments with it. For Part D, we started creating the scientific poster and began working on the promotional video.
Read More ->
public/team-building-team-collaboration-for-business-idea-teamwork-to-solve-problem-participate-to-work-together-for-success-concept-businessmen-and-businesswomen-team-up-to-solve-lightbulb-jigsaw-vector-1500w.jpg

Progress Update - 26th May - 1st Jun.

This week, in Part A, a load management algorithm for general load profiles was developed and completed, along with an algorithm to assess the global impact on the load diagram. Adjustments were made to the user interface, and the load management algorithm was integrated with blockchain transactions. In Part C, the 3D model printing was completed, and we began the construction of the physical model. In Part D, aesthetic improvements and new features were added to the project website.
Read More ->
public/team-building-team-collaboration-for-business-idea-teamwork-to-solve-problem-participate-to-work-together-for-success-concept-businessmen-and-businesswomen-team-up-to-solve-lightbulb-jigsaw-vector-1500w.jpg

Progress Update - 19th May - 25th May

This week, we made progress in Part A: we continued to work on the load management algorithms, made adjustments to the implementation of the predictive model for energy prices, including updates to the corresponding technical documentation. Additionally, in Part D, improvements were made to the website in terms of functionality and aesthetics, aiming for a better user experience.
Read More ->
public/team-building-team-collaboration-for-business-idea-teamwork-to-solve-problem-participate-to-work-together-for-success-concept-businessmen-and-businesswomen-team-up-to-solve-lightbulb-jigsaw-vector-1500w.jpg

Progress Update - 12th May - 18th May

In Part A, we continued the implementation of the transaction and battery management algorithm. We also finalized the User Interface. In Part C, we designed the electrical schematic for the mock-up. Lastly, in Part D, we commenced the development of the project demonstration video.
Read More ->
public/team-building-team-collaboration-for-business-idea-teamwork-to-solve-problem-participate-to-work-together-for-success-concept-businessmen-and-businesswomen-team-up-to-solve-lightbulb-jigsaw-vector-1500w.jpg

Progress Update - 05th May - 11th May

This week, in Part A we made progress on implementing the transaction and battery management algorithm and adjusted the User Interface. In Part C, we completed the Arduino programming, although further adjustments might be needed after finalizing Part A. We will continue testing and refining the algorithm, improving the User Interface, and adjusting the Arduino programming as necessary to ensure seamless integration of all components.
Read More ->
public/team-building-team-collaboration-for-business-idea-teamwork-to-solve-problem-participate-to-work-together-for-success-concept-businessmen-and-businesswomen-team-up-to-solve-lightbulb-jigsaw-vector-1500w.jpg

Progress Update - 28th Apr. - 04th May

This week, in Part A, we developed technical documentation for implementing the Machine Learning model for forecasting energy consumption and price. Additionally, we continued implementing the transaction and battery management algorithm. The implementation of the user interface was also continued. In Part C, we continued the work from last week.
Read More ->
public/team-building-team-collaboration-for-business-idea-teamwork-to-solve-problem-participate-to-work-together-for-success-concept-businessmen-and-businesswomen-team-up-to-solve-lightbulb-jigsaw-vector-1500w.jpg

Progress Update - 21th Apr. - 27th Apr.

This week in Part A, we developed technical documentation for the statistical analysis of variables. Additionally, we began implementing the transaction and battery management algorithm. The creation and configuration of the user interface were also started. In Part C, the focus during these two weeks was primarily on Arduino simulations.
Read More ->
public/team-building-team-collaboration-for-business-idea-teamwork-to-solve-problem-participate-to-work-together-for-success-concept-businessmen-and-businesswomen-team-up-to-solve-lightbulb-jigsaw-vector-1500w.jpg

Progress Update - 14th Apr. - 20th Apr.

This week, in Part A, was made the integration of the three predictive Machine Learning models (consumption, production and price). In Part C, we continued the work from last week.
Read More ->
public/team-building-team-collaboration-for-business-idea-teamwork-to-solve-problem-participate-to-work-together-for-success-concept-businessmen-and-businesswomen-team-up-to-solve-lightbulb-jigsaw-vector-1500w.jpg

Progress Update - 07th Apr. - 13th Apr.

This week, in Part C, we worked on size adjustments to the previously identified 3D models. We also finalized our digital model of the 3D prototype and compiled the final list of materials required for its realization.
Read More ->
public/team-building-team-collaboration-for-business-idea-teamwork-to-solve-problem-participate-to-work-together-for-success-concept-businessmen-and-businesswomen-team-up-to-solve-lightbulb-jigsaw-vector-1500w.jpg

Progress Update - 31th Mar. - 06th Apr.

During the next two weeks, in Part A, our attention will be focused on preparing for exams. A general group meeting was held to better define the next steps and organization. In Part B, we wrote documentation related to the implementation of blockchain transactions.
Read More ->
public/team-building-team-collaboration-for-business-idea-teamwork-to-solve-problem-participate-to-work-together-for-success-concept-businessmen-and-businesswomen-team-up-to-solve-lightbulb-jigsaw-vector-1500w.jpg

Progress Update - 24th Mar. - 30th Mar.

This week, we prepared the pitch deck for the mid-term evaluation and made adjustments to the machine learning models in Part A and 3D modeling of the prototype in Part C.
Read More ->
public/team-building-team-collaboration-for-business-idea-teamwork-to-solve-problem-participate-to-work-together-for-success-concept-businessmen-and-businesswomen-team-up-to-solve-lightbulb-jigsaw-vector-1500w.jpg

Progress Update - 17th Mar. - 23th Mar.

Continuing from last week, our focus remains on refining load profiles and acquiring data for machine learning and statistical analysis. We're improving base load profiles' accuracy and specificity while gathering necessary data for each profile. Additionally, we're advancing the normalization and scaling of load profiles to mirror the national context, considering variables like EV quantity and installed charging power.
Read More ->
public/team-building-team-collaboration-for-business-idea-teamwork-to-solve-problem-participate-to-work-together-for-success-concept-businessmen-and-businesswomen-team-up-to-solve-lightbulb-jigsaw-vector-1500w.jpg

Progress Update - 10th Mar. - 16th Mar.

This week, we're dedicated to enhancing our understanding of load profiles through machine learning and statistical analysis. We're refining base load profiles and gathering essential data for comprehensive modeling and analysis.
Read More ->
public/team-building-team-collaboration-for-business-idea-teamwork-to-solve-problem-participate-to-work-together-for-success-concept-businessmen-and-businesswomen-team-up-to-solve-lightbulb-jigsaw-vector-1500w.jpg

Progress Update - 3rd Mar. - 9th Mar.

This week, we continued our work from last week on the development of the energy market model. We progressed with data acquisition and initial analysis for machine learning model development, while also starting discussions on integrating these outcomes into our project. Additionally, we began developing the energy market model, focusing on market dynamics and pricing data. Furthermore, in Part B, we concluded the study on how blockchain chains and smart contracts function, as well as the research on the legal conditions our project could face in the future.
Read More ->
https://aheioqhobo.cloudimg.io/v7/_playground-bucket-v2.teleporthq.io_/507de827-6d83-4350-867b-fff98f0458e9/be6d274b-ff36-45c1-982a-29ba4b492187?org_if_sml=184875&force_format=original

Progress Update - 25th Feb. - 2nd Mar.

During this week we focused on energy production data acquisition and initial analysis for machine learning model development. Discussions began on integrating these results into our project. Additionally, we initiated the development of an energy market model, studying energy market dynamics and data analysis for pricing.
Read More ->
public/external/team-building-team-collaboration-for-business-idea-teamwork-to-solve-problem-participate-to-work-together-for-success-concept-businessmen-and-businesswomen-team-up-to-solve-lightbulb-jigsaw-vector-1500w-200h.jpg

Progress Update - 18th Feb. - 24th Feb.

During this week, in Part A, we worked on machine learning for energy consumption, including data acquisition, analysis, and the development of a prediction model. We also started discussing how to integrate these results into the project. In Part B, we focused on understanding blockchain technology and smart contracts, researching legal implications, and creating the necessary code for transactions. Additionally, in Part B, we continued the study on how blockchain chains and smart contracts function, and we furthered our research on the legal conditions our project could face in the future.
Read More ->
public/team-building-team-collaboration-for-business-idea-teamwork-to-solve-problem-participate-to-work-together-for-success-concept-businessmen-and-businesswomen-team-up-to-solve-lightbulb-jigsaw-vector-1500w.jpg

Progress Update - 11th Feb. - 17 Feb.

This week, we focused on exploring V2G technology and its potential impact nationally, alongside beginning the study of how blockchain chains and smart contracts function. We delved into its main features, challenges, and implications, including its role in decarbonizing transportation and achieving carbon neutrality. Additionally, progress was made in developing project documentation and preparing for the website launch, while initiating, in Part B, research on the legal conditions our project could face in the future.
Read More ->